Construction and Renovation Works for Urban Conservation Area and Göbeklitepe Archeological Site in Şanlıurfa FIDIC Contract

Structural Steel Canopy Construction within the preservation plan of the Göbeklitepe Archaeological Site.

The T shaped pillars carved from locally quarried limestone reserves are proven to be the earliest evidence of man-made buildings of prehistoric human populations dating back to 10th-9th millennium BC. These monuments are a testimony on the history of the transition from hunting communities to agrarian societies. Monumental Stone Age Architectural Site has been included in the World Heritage List.

Location

Şanlıurfa, Türkiye

Year
2017
Key Responsibilities
  • Monitor progress and quality of works, inform Contracting Authority of any problems re costs and time
  • Provide quality control, inspection of works and materials
  • Instruct the Contractor for any necessary additional or modified drawings
  • Monitor the Contractors quality Control programmes
  • Check the quality of the works, built-in materials and installed plants
  • Review and approve Contractor’s material submittals, check country of origin
  • Measure and keep accurate records of completed works, detail deviations
  • Witness test of construction materials, keep records of results
  • Liaise with Relevant Authorities for testing and inspection programme
  • Maintain Financial Control
  • Review Contractors programme and cash flow predictions to assist Contracting Authority re funds
  • Check, approve Contractors Interim Payment applications, issue payment certificates
  • Advise Contracting Authority on receipt of Contractors claims for additional payments/extension of time
  • Issue variation orders if no change in cost/extension of time and if approved by Contracting Authority
  • Advise, seek approval of Contracting Authority for variation orders where cost/ext of time is involved
  • Report to Contracting Authority on disputes that require their intervention/assistance
  • Monitor Progress of the works, hold weekly progress meetings with Contractor
  • Prepare and submit all specified reports as required
  • Maintain Health and Safety and Environmental Control
  • Maintain Document Control, daily records, as-built drawings, quality dossier
  • Daily record site events into logbook, check Contractors site diary
  • Organise monthly progress meetings, distribute minutes, attend other meetings as reqd.
  • Assist, give advice to Contracting Authority and obtain specific approval where specified in ToR